Venice Canal Water System Improvement Project – 12/19 update

Here is the latest update from Jesus Gonzalez, LADWP project manager:

Hello Everyone,

First off, I’d like to thank everyone for your patience during our construction. In spite of all the challenges we’ve encountered, our construction crews have made very good progress the past few weeks.

With regard to the our upcoming work, we’ve adjusted our schedule to minimize the impact to all of the residents during the holiday season. With that said, we will NOT work on 12/24, 12/25, nor 1/1/15. As for the specific work on Courts E and D:

  • Construction on Court E – The work on Court E is 95% complete, and we are scheduled to complete all the work this Tuesday 12/23. The only remaining work is to finish the paving of the street, which will take place this Monday (12/22) and Tuesday.
  • Construction on 200 Block of Court D – We will start construction on Court D on Tuesday, December 30th. We have distributed parking passes, however if you did not receive them, or if you need additional passes, please contact me.

Thank you again, and on behalf of DWP, Happy Holidays!



Both comments and pings are currently closed.